Risk #2070

Updated by Vyacheslav Mukhortov over 3 years ago

|_.Description 
 Описание|Due |_.Description|Due to lack of time for business analysis, there is a big risk that some critical requirements have not been identified| 
 |_.Impact 
 Влияние на проект|Additional |_.Impact|Additional time and budget for implementing missing requirements| 
 |_.Indicators 
 Индикаторы|The |_.Indicators|The risk is considered to have happened if during the acceptance of the user interface prototype developed at Elaboration stage it appears clear that some forms or form elements are missing| 
 |_.Mitigation actions 
 Действия по смягчению|1. actions|1. Track all the requirements in redmine, get customer approval for each requirement 
 2. Elaborate user interface prototype and get customer approval prior to implementing the requirements| 
 |_.Contingency plan 
 План устранения последствий|In plan|In the risk happens, the following tasks are to be performed: 
 1. UI prototype refactoring - 16 m/h 
 2. Getting customer approval for an updated UI prototype – 8 m/h 
 3. Project estimate revision – 8 m/h| 
 |_.State of affairs 
 Состояние дел| affairs| Requirement #2040 has been changed (see #2040 p.6). UI prototype refactoring is in progress. |