Risk #2070
openMissing requirements due to incomplete business analysis
Mitigation strategy:
Contain
Risk rank:
High
Risk type:
Known
Actual Risk Impact (m/h):
Change status:
Description
| Description Описание |
Due to lack of time for business analysis, some critical requirements may be missed |
|---|---|
| Impact Влияние на проект |
Additional time and budget for implementing missing requirements |
| Indicators Индикаторы |
The risk is considered to have occurred if, during the acceptance of the user interface prototype developed at Elaboration stage it turnes out that some forms or form elements are missing |
| Mitigation actions Действия по смягчению |
1. Track all the requirements in redmine, get customer approval for each requirement 2. Elaborate user interface prototype and get customer approval prior to implementing the requirements |
| Contingency plan План устранения последствий |
The following tasks are to be performed in case if the risk occurs: 1. UI prototype refactoring - 16 m/h 2. Getting customer approval for an updated UI prototype – 8 m/h 3. Project estimate revision – 8 m/h If the re-estimation causes the budget increase to exceed the 80 m/h reserve, all requirements must be reprioritized and some must be postponed for future releases. |
| State of affairs Состояние дел |
Requirement #2040 has been changed (see #2040 p.6). The new requirement #6197 has been added. 1. UI prototype refactoring #8725 - in progress. |
Updated by System/Data Analyst almost 7 years ago
- Status changed from New to Analysis
Updated by System/Data Analyst almost 7 years ago
- Status changed from Analysis to Analysis completed
Updated by System/Data Analyst about 6 years ago
- Description updated (diff)
- Status changed from Analysis completed to Triggered
Updated by Vyacheslav Mukhortov about 5 years ago
- Related to Requirement #2040: Authorization (login) added
Updated by Project Manager over 3 years ago
- Related to Task #8725: UI Prototype refactoring added
Updated by Project Manager over 3 years ago
- Related to Requirement #6197: User Activity Audit added
Updated by Vyacheslav Mukhortov over 2 years ago
- Subject changed from Missing requirements to Missing requirements due to incomplete business analysis
- Description updated (diff)
Updated by Vyacheslav Mukhortov over 2 years ago
- Risk type changed from Unknown to Known