Project

General

Profile

Issues

Filters

Apply Clear

Estimated time: 0.00 Spent time: 0.00 Actual Risk Impact (m/h): 0.00

# Tracker Status Priority Subject Assignee Updated Estimated time Spent time
1249TaskNewMiddle (Средний)ModelingSystem/Data Analyst2019-02-10 22:400.00
1248TaskNewMiddle (Средний)ConstructionProject Manager2019-02-10 22:400.00
1244TaskNewMiddle (Средний)Data PreparationSystem/Data Analyst2019-02-10 22:400.00
1243TaskNewMiddle (Средний)Elaboration2019-02-13 18:260.00
1242TaskNewMiddle (Средний)Preliminary planProject Manager2019-02-13 18:240.00
1241TaskNewMiddle (Средний)Data UnderstandingSystem/Data Analyst2019-02-10 22:400.00
1240TaskNewMiddle (Средний)Business understandingProject Manager2019-02-10 22:400.00
1238TaskNewMiddle (Средний)Inception2019-02-10 22:400.00
    (1-8/8)

    Also available in: Atom CSV PDF